Called Autostrada A3 (Romanian for, motorway A3 ' ), also Autostrada Transilvania (Romanian for, Transylvania Motorway '), is a future 588 km long highway on the route Bucharest - Ploiesti - Brasov ( Kronstadt) - Fagaras ( Fagaras ) - Sighisoara ( Sighisoara ) - Târgu Mureş ( Tirgu Mures ) - Cluj- Napoca ( Cluj ) - Zalău ( Zillemarkt ) - Oradea ( Oradea ) - Borş by Transylvania leads to the Hungarian border and is connected to the Hungarian motorway M4. You will also receive connection to the future Terminal 2 of the airport Otopeni.

For the use of motorways and national roads are generally acquired a vignette ( rovignetă ).

Progress

Full completion should be done originally in 2014. Due to problems with financing the compliance with which is has become impossible.

Sections in Transylvania

For the 415 km long motorway section Brasov - Oradea ( Borş ) of Works in 2004 was directly awarded by the Romanian government to the U.S. company Bechtel, without having previously made ​​a bid. The construction costs were set at 2.2 billion euros, with completion at the end of 2012. The first 42 km long section of Cluj- Napoca ( Gilău ) to Turda ( Thornburg ) was opened on 1 December 2009. On 13 November 2010, the ten kilometer long extension of Turda after Câmpia Turzii was opened to traffic. The Section 2B of the highway is now complete. In early 2010, the work was almost completely set; noisy construction company more than 200 million euros have not been paid by the Romanian state. In addition, the focus of investment in the construction of Highway 1 between the Hungarian border and Sibiu was favored because of this EU funding are available.

After the price per kilometer always continued to rise and the total estimated cost amounted to 9.9 billion euros, and in seven years only 52 km of motorway for 1.4 billion euros were completed, negotiated the Romanian state the contract with Bechtel in 2011 new. As a result, Bechtel should perform only the sections between Nădăşelu and Suplacu de Barcău and Suplacu de Barcău and the border with Hungary. Thus, the project was reduced to 112 kilometers. The remaining piece between Cluj and Nădăşelu was re-tendered. It represents an important gap closure for traffic to the north-west dar. Even with the distance of Turda direction Targu Mures should be the start of construction soon. Renewed contract negotiations between the State and Bechtel began in February 2013. On 30 May 2013, the Romanian government has the construction contract with Bechtel dissolved completely. But they had the U.S. company paid compensation in the amount of about 37 million euros and pay their debts worth 50 million euros. According to the Prime Minister Victor Ponta there so no more commitments and future plans for the completion of the sections could be made. It is planned to implement the sections of awarding concessions or public- private partnerships to various construction companies.

Section Bucharest - Brasov

Bucharest - Ploiesti

The planned completion of the section Bucharest - Ploiesti was expected in December 2011. According to the statement of the then Prime Minister Emil Boc early November 2011, this leg should be taken no later than spring 2012. However, this section was opened after a long delay until 19 July 2012.

Azuga - Brasov

The distance from Azuga to Braşov will lead along the villages of Sinaia, Buşteni, Predeal and Rasnov.

The tender should be prepared in 2012. In February 2013 a new call was launched. The section is now built into the framework of a concession. The contract should be signed before October 2013 so that construction could begin a month later. However, the deadline was extended until the submission of tenders until December 9. On 19 December it was decided to award. The contract was awarded by the consortium consisting of the construction company Vinci, Strabag and actuator. The concession period will be 30 years. Construction is scheduled to take place in April 2014, with completion between 2016/2017.